| Bus Value | Topic | Status/Need | Team Lead | Notes | |
| 8 | Sec. 0 Intro/User Guide | Make Top Ten Tips to avoid problems | GL | Feedback = needs work. or retire | |
| 8 | Prog. 14 QCP and AWS | OK to Use, Add Pix | GH/JS | IMPROVED | |
| 8 | Sec. 6 Millwork | In Rework Now | JL | ||
| 5 | Sec. 5 Finishing | Outline submitted, reviewed existing. | JE | ||
| 5 | Sec. 8 Wall Surfacing | OK to Use | KG | DONE | |
| 5 | Sec. 10 Casework | OK to Use | BS/JL | DONE | |
| 3 | Sec. 1 Submittals | Start | May not be 1 hr. | ||
| 3 | Sec. 2 Care Storage | Start | May not be 1 hr. | ||
| 2 | Sec. 12 Historic Work | Start | |||
| 1 | Sec. 4 Sheet Products | Consolidate 4 existing | |||
| 1 | Sec. 3 Lumber | Start | |||
| 1 | Sec. 11 Countertops | Notes/Graphics | |||
| 1 | Sec. 9 Doors | Start | |||
| 1 | Sec. 7 Stairs and Rails | Start | |||
| TBD | LEED Programs for both audiences | Start | RZ | ||